Task 2 Plan Delivery (BEP + MIDP)

Turn requirements into a delivery plan the team can follow.

You are now stepping into the role of the Lead Appointed Party. In this task, you’ll translate the Owner’s EIR into a coordinated plan that makes delivery clear - what gets delivered, who delivers it, and when. You’ll also set up Work Packages so models can be verified against the agreed requirements later.

[Image of relationship between EIR and BEP in ISO 19650]
Your role - Lead Appointed Party + Appointed Party Output - BEP + MIDP + Work Packages linked to demo models

What you will do

1. Create the BEP

Define how the team will collaborate and deliver information.

2. Set up the MIDP

Organise deliverables by milestone - including document placeholders.

3. Create Work Packages

Group tasks and link the correct demo models for verification.

Step 1 - Complete the BIM Execution Plan (BEP)

Module - Docs

Access the pre-filled BIM Execution Plan (BEP) document provided in the Contract Documents.

This document already contains the required structure and guidance for this assignment. Your task is to work through the BEP and complete the highlighted Smart Fields.

  • Review the pre-filled BEP sections
  • Complete all highlighted Smart Fields in the BEP template
  • Ensure the BEP aligns with the information requirements defined in the EIR (Task 1)
Accessing the pre-filled BEP document

To complete the BIM Execution Plan, go back to the "BEP" section in the Contract Document.

BEP Document Location
Once located, the BEP sections will guide you through the task. Follow the instructions in each section and complete the highlighted Smart Fields.
Want to learn more about BEP?
View Lesson on Plannerly Academy

Step 2 - Create the Master Information Delivery Plan (MIDP)

Module - Scope

The MIDP organises what will be delivered, by whom, and when. It turns scope tasks into a delivery schedule. For this assignment, you’ll import an example MIDP from the Plannerly library to speed things up.

Required checklist
  • Import the MIDP: Scope > Add From Library > Plannerly Templates > Example Project Scope > Master Information Delivery Plan (MIDP) > Add
  • Reorder milestones so Pre-Construction is above Operation (recommended).
  • In the Drawing Package task, add one document placeholder: Site Plan.pdf.
Add the MIDP Template

Add the MIDP in the Scope from the Plannerly Library.

Library Selection MIDP Template
Reorder milestones

Click on a Milestone, drag Pre-Construction to the top.

Reordering Milestones
Complete document placeholders in the MIDP

To complete the Drawing Package, add one additional non-geometric document placeholder: Site Plan.pdf

Adding Placeholder 1 Adding Placeholder 2 Adding Placeholder 3
Add task dependencies

Switch to Timeline view and connect the remaining tasks.

Example: Create a dependency between VisualizationDrawing Package.

[Image of Gantt chart dependencies in construction] Timeline View 1 Timeline View 2
Want to learn more about MIDP?
View Lesson on Plannerly Academy

Step 3 - Create Work Packages and assign models

Modules - Scope + Verify

Work Packages group related deliverables and connect your Scope tasks to real models in Verify. This is what prepares the team to check whether the model meets the agreed information requirements.

[Image of BIM work package structure]
Before you create Work Packages

Make sure every task is assigned to a delivery team. The imported MIDP is already assigned to Architect and Contractor teams. For the tasks you created in Task 1, assign each task to the appropriate team (Architect or Contractor).

Assigning Teams 1 Assigning Teams 2
Required checklist
  • Create a Work Package filtered to Architect team named Architecture WP.
  • Create a Work Package filtered to Contractor team named MEP WP.
  • Assign demo models: Architecture WP → Plannerly-Arc.rvt, MEP WP → Plannerly-MEPF.rvt.
Create two Work Packages
  1. In All Scope, add a new Work Package filtered to the Architect team and name it Architecture WP.
  2. Add a second Work Package filtered to the Contractor team and name it MEP WP.
Creating WP 1 Creating WP 2
Assign models to Work Packages
  • Architecture WP → Assign Plannerly-Arc.rvt (demo model)
  • MEP WP → Assign Plannerly-MEPF.rvt (demo model)
Assigning Models
That’s it - your delivery plan is ready. Next, you’ll move into verification and check what passes, what fails, and what changed.

Final deliverable checklist

  • The BEP is completed and reflects the EIR and project delivery approach.
  • The MIDP is imported, milestones are ordered clearly, and Site Plan.pdf is added as a document placeholder.
  • Architecture WP and MEP WP exist and are linked to their correct demo models.
  • You exported your completed BEP document - including the MIDP with timeline - in File Manager.
Export BEP + MIDP timeline to File Manager

Export your completed BEP document, including the MIDP with Timeline in File manager as a single Appointment document.

Exporting BEP